INVITATION TO BID:
SKANSKA USA BUILDING - SUMNER HIGH SCHOOL ADDITION PH2
MACC II BID PACKAGE
BP 04A - MASONRY
BP 06B - MILLWORK AND FINISHED CARPENTRY
BP 07A - ROOFING & ACCESSORIES
BP 07F - EXTERIOR SIDING
BP 08A - DOORS, FRAMES, AND HARDWARE
BP 08D - WINDOWS, STOREFRONT AND GLAZING
BP 09A - FRAMING, SHEATHING, & AIR BARRIER
BP 09D - TILE FINISHES
BP 09E - ACOUSTIC & SPECIALTY CLNGS
BP 09G - INTERIOR PAINT AND WALL COVERINGS
BP 09H - EXTERIOR PAINTING
BP 10A - MISC. SPECIALTIES & CARPENTRY
BP 11A - FOOD SERVICE EQUIPMENT
BP 13I - MODULAR BUILDING & COMPONENTS
BP 21A - FIRE PROTECTION
BP 23L - HVAC & PLUMBING
BP 26A - ELECTRICAL
BP 31A - EARTHWORK & UTILITIES
BP 32B - SITE HARDSCAPES & SITE FURNISHINGS
BP 32C - LANDSCAPING
Sumner-Bonney Lake School District – Sumner High School Addition PH2
Sealed bids will be received by Skanska U.S.A. Building, Inc. for construction subcontracts to the GC/CM Contract between Skanska U.S.A. Building, Inc. and Sumner-Bonney Lake School District for the above listed Scopes of Work. Deliver sealed bids to:
Sumner School District Maintenance
19701 104th St. E.
Bonney Lake WA 98391 Attention: Zach Wasielewski
Bid Dates and Times are as stated below:
BID PACKAGES DUE DATES
Bids Due on July 2nd, 2026
BP 04A - MASONRY - 9:00AM
BP 06B - MILLWORK AND FINISHED CARPENTRY - 2:00PM
BP 07A - ROOFING & ACCESSORIES - 1:00PM
BP 07F - EXTERIOR SIDING - 9:00AM
BP 08A - DOORS, FRAMES, AND HARDWARE - 11:00AM
BP 08D - WINDOWS, STOREFRONT AND GLAZING - 10:00AM
BP 09A - FRAMING, SHEATHING, & AIR BARRIER - 8:00AM
BP 09D - TILE FINISHES - 1:00PM
BP 09E - ACOUSTIC & SPECIALTY CLNGS - 10:00AM
BP 09G - INTERIOR PAINT AND WALL COVERINGS - 11:00AM
BP 09H - EXTERIOR PAINTING - 11:00AM
BP 10A - MISC. SPECIALTIES & CARPENTRY - 1:00PM
BP 11A - FOOD SERVICE EQUIPMENT - 10:00AM
BP 13I - MODULAR BUILDING & COMPONENTS - 2:00PM
BP 21A - FIRE PROTECTION - 9:00AM
BP 23L - HVAC & PLUMBING - 8:00AM
BP 26A - ELECTRICAL - 8:00AM
BP 32B - SITE HARDSCAPES & SITE FURNISHINGS - 2:00PM
BP 32C - LANDSCAPING - 2:00PM
Bids will then be publicly opened and read aloud five minutes after the bid due time. Bids received after the dates and times stated above WILL NOT receive consideration.
PRE-BID CONFERENCES
A non-mandatory, though highly encouraged pre-bid conference will be held at the following location for all Group II Bid Packages. Pre-Bid Meeting will start at 3:00pm on June 9th, 2026.
Location: Parking Lot off of Wood, Sumner High School 1707 Main St, Sumner, WA 98390
Contract Documents for this work may be obtained online through Building Connected. They will be available Thursday, June 4th, 2026; the documents will also be posted online at Builder's Exchange of Washington (www.bxwa.com) under Posted Projects/General Contractor Project areas/Washington/Skanska/Projects Bidding.
Questions that develop during the bid period must be submitted in writing and or emailed to Skanska USA Building, Inc. to taylor.lyman@skanska.com. All questions and answers will be published via addenda during the bid period. Questions must be received no later than 2:00 PM on June 16th, 2026. DO NOT present questions directly to the Architect/Engineer or the School District.
A bid guarantee of 5% of the total bid amount is required at the time of bid. Bid deposits may be submitted in the form of a Bid Bond or cashier's check, made to Skanska U.S.A. Building, Inc.
BUSINESS EQUITY: The project is committed to providing the maximum practicable opportunity for participation in contracting by small business entities and disadvantaged business enterprises. That commitment includes maximizing opportunity for state-certified minority business enterprises (MBEs) and women business enterprises (WBEs) on public works construction projects (collectively referred to as MWBEs). Participation may be either on a direct basis or as a subcontractor or supplier.
RETENTION: Skanska plans to obtain a Retention Bond for the project. Subcontractors will have the option of participating in the Skanska retention bond in lieu of having retention held. Those who do not participate will be held to the standard 5% retention.
Skanska USA Building, Inc. reserves the right to reject any or all bids and to waive any non-material informalities or irregularities in the bids received. A bidder may withdraw its proposal by submitting a written request before the bid opening time. Skanska will return the proposal unopened after contract award.
IPL0347034