San Juan Water District
INVITATION TO BID
Sealed proposals will be received at the office of the San Juan Water District, located at 9935 Auburn Folsom Road, Granite Bay, CA 95746, until 2:00 p.m. local time on September 24, 2026, or such later date as may be set by addendum, and then will be publicly opened and read for the construction of the following public works project:
Hinkle Reservoir Embankment Restoration and Repair Project.
In general, the nature of the work involves the repairing and armoring of the Hinkle Reservoir dam embankment slope and restoration of the existing swale at the toe of the embankment. The Project is located at the District's Water Treatment Plant's Hinkle Reservoir located at 9935 Auburn Folsom Road, Granite Bay, Placer County, CA. Work is divided into three locations (Schedule A, B, and C). Schedule A and Schedule C work shall be completed within 90 calendar days from the date on the Notice to Proceed. Schedule B work must commence after May 1, 2027 and be completed on or before June 1, 2027. The Contract Documents contain a full description of the Work, and requirements.
The contract documents for the Project, including the public works construction contract, instructions to bidders, bid forms, and plans and specifications, may be examined at the District office, with prior notice to the District's representative, located at 9935 Auburn Folsom Road, Granite Bay, CA 95746. An electronic copy of contract documents may be obtained from the website www.publicpurchase.com. Bidders must comply with the Instructions to Bidders.
The District will hold a mandatory pre-bid conference and site walk at the District's offices located at 9935 Auburn Folsom Road, Granite Bay, CA 95746, on September 10, 2026 at 11:00 a.m.. It is suggested that each prospective bidder review the bid documents prior to the pre-bid conference. Each prospective bidder shall be required to attend the pre-bid conference. Bids from any bidder not attending this conference will be rejected as non-responsive. Any questions may be addressed in writing via e-mail to the District representative. Questions are due on or before September 17, 2026 at 3:00 p.m..
District Representative:
Mark Hargrove, P.E. San Juan Water District
Engineering Manager Engineering Services Department
mhargrove@sjwd,org 9935 Auburn-Folsom Road
Phone: (916) 791-6951 Granite Bay, CA 95746
Dated this 31st day of August 2026
San Juan Water District
By: Mark Hargrove, Engineering Managert
IPL0369919
Aug 31,Sep 7 2026