NTTA
RFB 06286-NTT-00-CN-PD
DNT & SRT Bridge Deck
Joint Seal Repairs, Phase 2
Project Description: Bridge joint seal replacement for main lane and direct connector bridges on DNT from Harvest Hill Road to PGA Parkway and mainline, direct connector and frontage road bridges on SRT from Denton Tap Road to Business 121. Remove and replace existing bridge deck joint seals and reseal approach slab expansion joints. Repair
damaged bridge deck joints and damaged concrete adjacent to bridge and approach joints at select locations.
The North Texas Tollway Authority (NTTA) is accepting bids for the above mentioned solicitation until 11/20/2025 at 11:00 a.m. CT. Bidders are encouraged to upload their bids to NTTA's Marketplace (https://www.nttamarketplace.org). Bids will be read at a virtual bid opening meeting on 11/20/2025 at 3:00 p.m. CT. See RFB documents for meeting details.
A virtual pre-bid conference will be held on 11/10/2025 at 2:30 p.m. CT. See RFB documents for meeting details.
Email bidpurchasing@ntta.org for questions on registration or use of website.
IPL0282380
Oct 17,24 2025